GRASS RESIDENCES MILESTONES
  • Tower 1 - Topping off ceremony on March 6, 2010.
  • Tower 3 - excavation activity still in progress
  • On going construction of the Bridgeway connecting Grass to SM North Edsa

Grass Tower 1 Topping Off Ceremony Annoucement on
PHILIPPINE DAILY INQUIRER

Philippine-Daily-Inquirer


Ongoing Brideway construction connecting Grass and
SM North Edsa Construction (Along Misamis St.)
Bridgeway-Construction-Misamis

Ongoing Brideway construction connecting Grass and
SM North Edsa Construction (Inside Grass Site)
(gray concrete pillars)
Bridgeway-Construction-Inside